A resource profile is the work capacity of a given resource base on the Type of Work. That is, it tells the DMS scheduler what work a resource can do for a given shift, day and week. A resource can have zero or more resource profiles, but should have at least one resource profile or it cannot be used by the schedule.
The screen example below shows a resource profile for the type of work "Regular Work" for the Assembly labor resource. Note that in the "Current profiles:" list the "Regular Work" has a "(d)" next to its name. This informs you that the "Regular Work" profile is the default profile for this resource. The default profile is the profile that is used by the scheduler if you do not specify which type of work to use at either the job, operation, or schedule level.
To add a new resource profile, click the Add a New Profile button. To edit an existing profile, click on the existing profile in the Current profiles: list box and the current profile will be displayed.
To add a new profile, perform the following steps:
You can click on File | Delete or the delete icon to delete an existing resource profile. For example, to delete the resource profile "Max Overtime" for a given resource you would select the resource in the tree view by clicking on the resource, select the "Max Overtime" profile from the Current profiles lst box and then select delete. DMS will confirm the delete with a window as follows:
If you click OK, the resource profile will be deleted. Click Cancel to cancel the delete. Note that you cannot delete a profile that is used by an operation; however, you can make a resource profile unavailable for future use by removing the check for the Available prompt for the resource profile.