Capacity Resource Planning (CRP) is a schedule run that looks at backlog. CRP will infinitely load jobs on resources up to one year previous to the entered "Today's Start Date". The main purpose of a CRP schedule is to analyze the discrepancy between the capacity of an organization and the demands of its customers. It can show both the under-utilized resources (load less than capacity) and unfulfilled customers demand (load greater than capacity).
To run a CRP schedule, select a CRP schedule run from the Scheduler.