Schedule Horizon
Previous Topic  Next Topic 

The schedule horizon is the number of days out from the schedule start date you want to generate a finite schedule. If you are scheduling jobs out for 1 year for example you may select 365. Jobs that fall outside this horizon will automatically be scheduled infinitely. A finite schedule takes longer to calculate than an infinite schedule.  The maximum schedule horizon is 1825 days (about 5 years).