The following symbols and bars are used on the Gantt Charts:
|
The Release date of the job. |
|
The due date of the job. If in-process, the due date will be a green diamond |
|
Baseline job start date. |
|
Baseline job end date. |
|
Last scheduled completion date (LSC Date). |
|
Job Promise Date. |
|
Job or Operation Material Date. |
|
Shows the start date of the job to the completion date of the job. |
|
Shows the start date of the job to the completion date of a late job. |
|
Shows the start date to the completion date of an in-process job. The green bar shows the percentage completion for the job. In this example, the job is about 50% complete. |
|
Shows the start date to the completion date of an in-process late job. The green bar shows the percentage completion for the job. In this example, the job is about 90% complete. |
|
Shows a job bar with a that is projected to be late. The red diamond shows the due date. Since the due date is in the future compared to the current date, the job is not physically late but projected to be late. |
|
Shows a job bar that is projected to be late. The vertical black line represents the current date and the red diamond shows the due date. Since the due date is in the future compared to the current date, the job is not physically late but projected to be late. |
|
Shows a schedule operation from the operation start date to the operation’s end date. |
|
Shows a scheduled in process operation from the operation start date to the operation end date. The light green shows the percent complete for the operation. |
|
Shows a completed operation. If an operation is completed and there are not any actual dates, the operation’s schedule dates are used to graph the operation bar. |
Placing the mouse over a bar or milestone will display the bar/milestone’s hint giving detail on the job/operation.