Linked Operations schedules two or more operations together. The operations must be on the same resource and must be in different jobs. One operation is selected as the Parent operation and its job should have a high priority and earlier due date than the other linked operations. When the parent linked operation is scheduled, the other linked operations are scheduled with it.
Linked operations can either:
A linked operation can break away from the Parent if the linked operation’s start and end date are out of sequence its job’s operation flow. If the Break Link is selected, an operation can break away from the parent if it does not fit in its job’s flow. If Break Link is not selected, the operation must be scheduled with the parent and if its dates are out of sequence in the job, the scheduler will print a warning message. Note that if an operation breaks away from its parent, if extra runtime was added for the operation’s time is not removed from the parent’s total schedule time.
Linked operations can be selected from: