Set Baseline Dates

 

 

The Set Baseline Dates enables you to set Job Baseline Dates to the job’s current schedule dates and/or to set Operation Baseline Dates to the operation’s current schedule dates.

 

From Mfg Orders Job Grid, select Grid Tools | Set Baseline Dates.

 

The following example shows the Set Baseline Dates Window:

 

 

To Set Baseline Dates, the following commands are entered:

1.Use Mfg Orders Job Grid Selections  Select this checkbox to update the current jobs listed in the Mfg Orders Job Grid.  If selected, The Order Number Selection prompt and Select Job States to Set Baseline Dates prompt are grayed out.

2.Order Number Selection  Enter the Order Number to set baseline dates.  The SQL wild cards % and _ (underscore) can be used in the Order Number.  The Order Number can be left blank if the Set Baseline Dates is going to be performed by Job States.  Both Order Number and the Job States can be given.

3.Select Job States to Set Baseline Dates  Use the drop-down menu to select the Job States that are to have their baseline dates set.

4.Set Job Baseline Date  Select this checkbox to set Job Baseline Dates.

5.Only Set Job Baseline Dates if Blank  Select this checkbox to only set blank Job Baseline Dates.

6.Set Operation Baseline Date  Select this checkbox to set Operation Baseline Dates.

7.Only Set Operation Baseline Dates if Blank  Select this checkbox to only set blank Operation Baseline Dates.

8.If blank operation schedule dates, set to  If the Set Operation Baseline Dates is selected, blank operation schedule dates can also be set.  One of four options can be selected:

1.Leave schedule dates blank

2.Set blank schedule dates to job release date

3.Set blank schedule dates to job schedule start date

4.Set blank schedule dates to new date: (New Date)

 

 

See also:

 

Auto Set Baseline Dates