Job Gantt Chart
Previous Topic  Next Topic 

The Job Gantt Chart displays the current jobs in the Manufacturing Orders Job Grid in a Gantt chart.  For the definition of symbols used on chart, please refer to the Job Gantt Chart Legend.


Select the Job Gantt Chart by either File | Graphs | Job Gantt or by using Graphs | Job Gantt.  The first 50 jobs will be loaded into the Job Gantt as per the screen example below:



50 jobs are loaded at a time to reduce the system resource requirements and speed up the loading process.  After the jobs are loaded, the Job Gantt appears. 


Capacity changes are shown on the chart by vertical colored bars as follows; pools capacity change in light yellow, department capacity change in brown, resource capacity change in light orange, and calendar capacity changes in green. Capacity changes are shown only in the time scales of Shifts and Days.  Pool, department and resource capacity changes do not show the name of the effected pools, department or resource as many items may be part of the change.  Calendar capacity changes show the comment of the corresponding capacity change. 


If several capacity changes are on the same day, Calendar capacity changes take precedence over the other changes, than Resource changes are shown, than Pool changes are shown, and finally Department changes are shown.  Capacity changes are shown from the schedule start date forward 1 year. 


The example below shows the Job Gantt Chart:



A right click will display the popup menu shown below.



Valid commands are:


  1. Go to Bar Start  The popup menu command will move the Gantt chart to the start of the current bar.
  2. Go to Bar End  The popup menu command will move the Gantt chart to the end of the current bar.
  3. Go to Release Date  The popup menu command will move the Gantt chart to the selected job's release date .
  4. Go to Job Due Date  The popup menu command will move the Gantt chart to the selected job's due date.
  5. Material Display Use the right mouse button and select Material Display to display the material for the job using Material Display
  6. Edit Job Edit a job by double clicking on the job order number or the job bar, or highlight the job and select File | Edit Job or click on the edit icon .
  7. Edit Operations Edit a job's operations by double clicking on the operation or the operation bar, or highlight the operation and click on the edit icon .
  8. Runs With Jobs  A Runs With Job Group can be setup by selecting the job to be a runs with job and either select File | Runs With Jobs or right click on the Job Tree and select Runs With Jobs from the popup menu.  The Runs With Jobs Window appears.
  9. Update Job Update a job using Job Status Updating by highlighting the job or operation within a job and either select File | Job Updating or click on the job updating icon .
  10. Quick Job Updating To select Quick Job Updating, use the right mouse button and click on a job or operation in the job tree.
  11. Print Gantt  Select File | Print Gantt to print the current Gantt chart. 
  12. Print Report Select File | print Report to print a DMS Report as setup by Module Report Settings.
  13. Expand All  Right click on the job/operation tree and select Expand All from the pop up menu to expand all the jobs' operations in the graph.
  14. Collapse All  Right click on the job/operation tree and select Collapse All from the pop up menu to collapse all the jobs' operations in the graph.
  15. Job Expand Right click on the job/operation tree and select Job Expand from the pop up menu to expand the job's operations in the graph.
  16. Go to Job Start  Click on the Go to S.Start on the bottom of the graph or right click on the job/operation tree and select Go to Job Start to move the graph date scale to the start of the current job.
  17. Go to Today  Click on the Go to Today on the bottom of the graph to move the graph date scale to today's date.
  18. Go to Job End  Right click on the job/operation tree and select Go to Job End to move the graph date scale to the start of the current job.
  19. Hide Days  The Hide Days menu enable you to hide certain days of the week so they do not appear on the graph.  When you select days to hide or display, the graph does not need to redraw and the change takes place immediately.
  20. Display Selected Operations  You can select certain operations only to be displayed in the graph.  One of the following can be selected:
    1. Select View | Display All Operations to display all operations.
    2. Select View | Display Prime Only to display prime operations only. 
    3. Select View | Display Milestones Only displays only operations marked as Milestones.
  21. Sort  Jobs can be sorted in one of the following orders:
    1. Assembly (if displaying assembly jobs):
      1. Assembly Start Date
      2. Assembly End Date
    2. Order Number
    3. Part Number
    4. Part Number plus Start Date
    5. Job Identification
    6. Job Identification plus Start Date
    7. Start Date
    8. End Date
    9. Due Date
    10. Priority plus Due Date
  22. Time Scale The Time Scale for the graph can be one of the following:
    1. Days
    2. Weeks
    3. Months
    4. Quarters
  23. Click on the More Jobs to add the next 50 jobs to the graph.  After clicking on the button, jobs are loaded into the graph and the next 50 jobs are available to be viewed.
  24. Click the zoom in button to change the time scale to the next highest detail (quarters to months to weeks to days)
  25. Click the zoom to button to change the time scale to the next lowest detail (days to weeks to months to quarters)
  26. Job Gantt Display Options select View | Gantt Display Options to select display options for the Gantt Chart.
  27. Legend Select View | Legend to display the Job Gantt Chart Legend.


To display a bar or graph symbols details, hover the mouse cursor over the bar/symbol.  A popup hint will appear displaying details on the bar/symbol.  The example below shows a Gantt chart with a popup window giving details of a bar:



The screen below is an example of the display when the View | Legend is selected.  This displays shows all the symbols used in the Job Gantt Chart: