ETC Hours Display

 

 

The ETC Hours Display (Estimate to Complete) shows the work assigned to resources, pools, or departments from the current schedule start date out a given number of months.  When the ETC Hours Display appears, information is not displayed until the Search button is pressed.  The display can be dependent of the selections made in Manufacturing Orders Job Grid if the Use Mfg Orders Job Grid Selections is checked, or selections can be made using the Job Selections button. 

 

Job Selections are made to get a subset of work (projects) using the Job Identification and/or the Part Number.  The entered job identification and/or part number to search for will be displayed above the grid after the Search button is pressed. 

 

When the ETC Hours Display is selected, an empty grid appears as in the example below.  The first month in the column is the month of the last scheduled start date.  In the example below, the schedule was run with a schedule start in the month of August:

 

 

After Job Selections have been made or the Use Mfg Orders Job Grid Selections is checked, click on the Search button to perform the search.  It may take several minutes for the SQL search to be performed and the mouse cursor is changed to let you know the SQL search is taking place.  During the SQL search the system may appear to be not responding as DMS needs to wait for the search to be completed.  Once the search has been completed, the information is displayed as in the example below:

 

 

The following tabs and commands are available:

File

1.Jobs  Select Selections | Jobs to select jobs based on the job header information.  If selected, the Mfg Orders Job Grid automatically toggles off.

2.Search  Click on Search to perform the job search. 

3.Clear Selections  To clear your current search criteria, click on the Clear Selections button.  DMS will confirm the clearing of selections.

4.Number of Months  The number of months to display starting from the first day of the schedule.  The number of months to display can be from 1 month to 60 months.

5.Print Menu  Select File | Print Menu to print a DMS Report as set up by Module Report Settings.

6.Print Grid  Select File | Print Grid to print the current grid graph. 

7.Export Grid Contents 

 

View

1.Job Columns Reset  Select this command to reset all the ETC grid columns widths to the default.

2.Default menu tab

 

Selections

1.Jobs  Select Selections | Jobs to select jobs based on the job header information.  If selected, the Mfg Orders Job Grid automatically toggles off.

2.Search  Click on Search to perform the job search.

3.Mfg Orders Job Grid  Select Selections | Mfg Orders Job Grid to toggle on the option to include all jobs that were selected in the Mfg Orders Job Grid in the pie chart.

4.Clear Selections  To clear your current search criteria, click on the Clear Selections button.  DMS will confirm the clearing of selections.

5.Group  The Group menu item enables you to group resources into individual resources, Pools, or Departments.

 

Manufacturing

1.New Job  To add a new job.

2.Edit Job  To edit the first job in the Manufacturing Order job tree.

3.Calendar/Capacity Changes  are changes you want to make to the manufacturing calendar such as holidays, planned overtime, planned shut downs, etc.

4.Resources  is used to add, edit, delete resource settings.

5.Schedule Run  Run a global schedule.

6.Job Updating  is used to manually enter detailed time updates to a job.


Other commands include:

Certain types of resources can be excluded from the report.  If the drop-down menu of Exclude by resource type is selected, the following list appears:

 

 

One or more resource types to exclude can be entered.  For example, to exclude all resource types except Labor and Resource the following would be selected:


 

If resource type(s) to exclude are selected, the selection is saved by DMS between ETC Hours Display sessions.

 

The second last column on the right displays the total hours ("Total Hrs") for the resource and, at the bottom, the total hours of all resources. 

 

The last column on the right displays the resource totals past the number of months selected (i.e. if 12 months was selected, the last column would be >12 Months). 

 

The total heads per month is calculated by:

Total Hrs Per Month / Total Man Hours Per Month


Where the Total Man Hours Per Month is the number of week days x 8 hours.  The Total Man Hours Per Month does not include Saturdays or Sundays. 

 

If the Search button is pressed without making any jobs selections or if the Use Mfg Orders Job Grid Selections was not selected, DMS will warn the users with the following message:
 

 

You may continue with the search by selecting Yes, or click No to abort the search.  The above message will only appear once per session so subsequent searches without search criteria will not display this message.