BOM Link Display

 

 

The BOM Link Display shows BOM Linked jobs and all of the components.  When the BOM Link Display appears, information is not displayed until the BOM Link to display has been selected.  The BOM Link Display is selected from Mfg Orders Job Grid, Displays | BOM Link, or from the Job Analysis Graph by using the BOM LINK button that is displayed for BOM Linked jobs. 

 

The example below shows the BOM Link Display for the job MO-00056.  In this example, MO-00056 feeds two jobs; MO-00058 and MO-00060:

 

 

You can sort the grid by any column by clicking on the column header name.

 

The following tabs and commands are available:

File

1.New Job  Add a new job using Manufacturing Order Job Details.

2.Edit Job  Edit the selected job using Manufacturing Order Job Details.

3.Material Display  Select File | Material Display to display the material for the current selected job.

4.Print Menu  Select File | Print Menu to print a DMS Report as setup by Module Report Settings.

5.Print Grid  Select File | Print Grid to print the current grid graph. 

6.Export Grid Contents 

 

View

1.Default menu tab

 

Manufacturing

1.New Job  To add a new job.

2.Edit Job  To edit the first job in the Manufacturing Order job tree.

3.Calendar/Capacity Changes  are changes you want to make to the manufacturing calendar such as holidays, planned overtime, planned shut downs, etc.

4.Resources  is used to add, edit, delete resource settings.

5.Schedule Run  Run a global schedule.

6.Job Updating  is used to manually enter detailed time updates to a job.