Dispatch Display
Previous Topic  Next Topic 

The Dispatch Display shows the work assign to a resource for a given time period.  The dispatch is independent of the selections made in Manufacturing Orders Job Grid.  When the Dispatch Display appears, the default start date and end date are set to the first day of the schedule and the first resource (sorted alphabetically) is displayed on the screen.  The columns displayed are set in the Dispatch Display Grid Selections.


The example below shows a dispatch display for the resource Benching:



You can resize the columns by positioning the mouse over the bar between the columns in the heading and drag the column to the desired width. 


The following tabs and commands are available:


File

  1. New Job  Add a new job using Manufacturing Order Job Details
  2. Edit Job  Edit the selected job using Manufacturing Order Job Details
  3. Runs With Jobs A Runs With Job Group can be setup.  Select the job to be a runs with job and select File | Runs With Jobs.  The Runs With Jobs Window appears.
  4. Material Display  Select File | Material Display to display the material for the current selected job.
  5. Print Menu Select File | Print Menu to print a DMS Report as setup by Module Report Settings.
  6. Print Grid  Select File | Print Grid to print the current Grid graph. 
  7. Export Grid Contents 

 

View

  1. Job/Operation Columns  Select the jobs columns you want to see in the Job Grid.
  2. Default menu tab


Options

  1. Operations in Pools Only  Toggle this button on/off.  If On and a dispatch by pools is displayed, the operations must have the selected pool name.  If off, then any operation that uses a resource that is a member of the pool will be displayed.  That is, the operation does not specifically need to have the pool name specified; it will be displayed if the resource is a member of the pool.
  2. Sort The Sort menu item enables you to change the sort order of the information displayed in the dispatch grid.  Valid sort selections are:
    1. Start Date
    2. Start Date + Previous Operation Status
    3. Previous Operation Status + Start Date
    4. Start Date + Current Status + Previous Operation Status
  3. Group  the Group menu item enables you to group resources into individual resources, Pools or Departments.  Grouping will display all resources dispatch under the group selected.  For example, if you select a grouping of pools and then select a pool from the resource tree, the dispatch for all resources within the pool is displayed.


Manufacturing

  1. New Job to add a new job.
  2. Edit Job to edit the first job in the Manufacturing Order job tree.
  3. Calendar/Capacity Changes are changes you want to make to the manufacturing calendar such as holidays, planned overtime, planned shut downs, etc.
  4. Resources  is used to add, edit, delete resource settings.
  5. Schedule Run  Run a global schedule.
  6. Job Updating  is used to manually enter detailed time updates to a job.
  7. Start/Stop Clock  The Start/Stop Clock Updating is an alternate method to to update a job with times and quantities typically used by a timekeeper or shop floor personnel.
  8. Start/Stop Clock Edit  If using Start/Stop Clock Updating, the Edit Start/Stop Clock Job Updating enables an authorized user to edit existing start/stop clock entries. 



A right click on the Job Summary Grid will display the popup menu shown below.



Valid popup menu commands are:


  1. Edit Job Enables you to edit the current selected job.
  2. Link Operations Select this command to display the Linked Operations window to link two or more operations together.
  3. Edit User Field  The Edit User Field menu item will appear if you right click on a column that is a user field. For example, if a right click on the user field "Work Instruction" occurred, a window appears enabling you to change the user field.  Note that the user must have permission to edit user fields.
     


  4. Material Display Enables you to display the current material for the job.
  5. Quick Job Updating Select this command to display the Quick Job Updating window for the current selected job.
  6. Start/Stop Clock Job Updating Select this command to display the Start/Stop Clock Job Updating window for the current selected job.
  7. Update Job Select this command to display the Job Updating window for the current selected job.


Other commands:


  1. Resource A resource can be entered or selected from the Resource prompt or click on the resource tree to select a resource.
  1. Start Date The start date defaults to the first day of the schedule.  A new start date can be entered.
  1. End Date The start end defaults to the first day of the schedule.  A new end date can be entered.


The example below shows a dispatch display grouping by pools where the pool CNC 3+ Axis has been selected.  There are several different resources that are members of this pool: